The project construction will be completed in phases with Phase 1 consisting of installation of the prefabricated restroom building and Phase 2 consisting of completion of the sewage pump station and site work.
Phase 1 – December 2 through December 20, 2024 (Tentative):
Work planned during this phase includes building pad preparation, utilities work, and installation of the prefabricated restroom building. The existing asphalt pathway adjacent to the track and fields will be closed during this phase and a detour (see schematic map linked below) will be in place. Parking will be impacted along the detour route while the detour is in place. “No Parking” signs will be posted as needed. When this portion of work is completed, the detour will be removed, and the pathway will be reopened until Phase 2 construction operations begin.
Phase 2 – January/February 2025 (Tentative):
Fabrication of the pump station required for the restroom is estimated to take a couple of months. Once the pump components are fabricated tentatively by January/February of 2025, Phase 2 construction will occur including pumps installation and pathway paving. During this phase, it is estimated that the existing asphalt pathway adjacent to the track and fields will be closed again for 1-2 weeks, and the same detour will be in place.