The project construction will be completed in phases with Phase 1 consisting of installation of the prefabricated restroom building and Phase 2 consisting of completion of the sewage pump station and site work.
Phase 1 – December 2 through December 20, 2024 (Tentative):
Work planned during this phase includes building pad preparation, utilities work, and installation of the prefabricated restroom building. The existing asphalt pathway adjacent to the track and fields will be closed during this phase and a detour (see schematic map linked below) will be in place. Parking will be impacted along the detour route while the detour is in place. “No Parking” signs will be posted as needed. When this portion of work is completed, the detour will be removed, and the pathway will be reopened until Phase 2 construction operations begin.
Phase 2 – January/February 2025 (Tentative):
Phase 2 of the Cubberley Field Restroom site work is scheduled to begin construction on February 18, 2025 (tentative). City’s contractor completed installation of a prefabricated restroom building in December 2024 under Phase 1 construction. Phase 2 construction includes completion of the project with installation of a sewer pump station, water/sewer/electric utilities, and pathway paving.
The existing asphalt pathway adjacent to the track and fields will be closed during this phase and the same detour from Phase 1 (see schematic map linked below) will be in place. Parking will be impacted along the detour route while the detour is in place and “No Parking” signs will be posted as needed. The one-way drive aisle between the tennis court and buildings will also be closed to vehicle access while the detour is in place.
The work is anticipated to take approximately 2-3 weeks, weather permitting, and the pathway will be closed during this time.