PG&E Gas Pipeline Replacement Work Complete - July 2019

PG&E Gas Pipeline Replacement Work Complete - July 2019

In July 2019, PG&E completed the replacement of sections of its gas transmission pipeline that runs through Palo Alto. Work occurred from February through July 2019. Locations of the work and construction schedules are provided below. 

Safety is at the heart of everything we do—we appreciate your patience as we worked with PG&E to enhance the pipeline safety and reliability in your neighborhood.

About the Gas Pipeline Replacement Program in 2019 

PG&E conducted an in-line inspection of their gas transmission pipeline that runs from Palo Alto to Hillsborough in May 2018. The utility noted areas where parts of the pipe need to be repaired or replaced. In early 2019, PG&E began its work in Palo Alto and completed construction in July 2019. This work involved excavating around the existing underground pipeline and installing new pipe using industry-recognized and proven techniques. 

Contact Information

Please contact the PG&E project lead with any questions or concerns: 

Crystal Jewell, Pacific Gas and Electric Company

(408) 725.2240 office or crystal.jewell@pge.com 

To learn more about PG&E’s projects, visit pge.com/seeourprogress  


COMPLETED - Gas Pipeline Replacement Site 1: Loma Verde Avenue, from Kipling to Waverley

Timeline: Late February to mid-May 2019

Project Notification Letter

Map of Construction Area


COMPLETED -  Gas Pipeline Replacement Site 2:  2800 Block of Alma Street, Near El Dorado Avenue

Timeline: Late February to July 2019

Project Notification Letter

Map of Construction Area


COMPLETED -  Gas Pipeline Replacement Site 3: 195 Page Mill Road, between Park Boulevard and Sheridan Avenue

Timeline: Late February to end of July 2019

Project Notification Letter - March 28, 2019

Project Notification Letter - March 1, 2019

Project Notification Letter - February 1, 2019

Map of Construction Area


COMPLETED -  Gas Pipeline Replacement Site 4:  411 Page Mill Road, between Ash Street and El Camino Real

Timeline:  Mid-April to July 2019

Current Project Notification Letter - April 10, 2019

Project Notification Letter - March 15, 2019

Map of Construction Area


COMPLETED -  Gas Pipeline Replacement Sites 5 and 6: 1200 Page Mill Road

Timeline: Late April to end of July 2019

Map of Construction Area


COMPLETED -  Gas Pipeline Replacement Site 7:  Page Mill Road and Junipero Serra Boulevard

Timeline: Early May to end of July 2019 

Project Notification Letter

Map of Construction Area


Contact Information

Please contact PG&E at 1 (800) 743-5000 or the PG&E project lead with any questions or concerns: 

Crystal Jewell, Pacific Gas and Electric Company

(408) 725-2240 office, crystal.jewell@pge.com 

Why PG&E is Working in Palo Alto

The City of Palo Alto Utilities supplies electricity and natural gas to all residents and businesses in Palo Alto. However, we have to transport these commodities from where they originate to our town via pipelines and electric lines owned by Pacific Gas & Electric (PG&E). PG&E occasionally needs to perform maintenance on its gas or electric infrastructure. 