Churchill Avenue Enhanced Bikeway Project

  • Project typeTraffic and Transportation
  • Project value$3,580,679
  • Completion DateAugust 01, 2026

""  

Project Description

The Churchill Avenue Enhanced Bikeway is a Council-approved project and was identified as priority project in the Trails and Shared Use Pathways element of the City's 2012 Bicycle + Pedestrian Transportation Plan(PDF, 19MB). This connection provides a comfortable off-street bicycle route linking the Stanford Perimeter trail, Palo Alto Unified School District, the Castilleja-Park-Wilkie bicycle boulevards to downtown Palo Alto and Caltrain. These connections are of local and regional significance. Completing a missing link in a shared-use path will invite new bicycle travel, with associated reductions in greenhouse gas emissions, and traffic congestion. This project also includes safety improvements at the intersection of El Camino Real and Churchill Avenue. 

Scope of Work

  • Extend existing bicycle path on Churchill Ave from Castilleja to the Stanford Perimeter Trail
  • Add high visibility crosswalks at Castilleja
  • New lighting and curb improvements at Castilleja
  • Potential raised crosswalk (speed table) at Madrono
  • Restriping and repaving on Churchill
  • Landscaping/tree planting along school frontage
  • Remove pork chop island - Add a right turn only storage lane on westbound Churchill to northbound El Camino Real
  • Enhanced bicycle and pedestrian crosswalks at all 3 crossings of intersection of El Camino Real

 

Project Status

Staff has completed 100% of the design plans. Staff is working with the Palo Alto School District for the approval of an easement and with Caltrans for an Encroachment Permit in order to complete the final design and begin construction. 

Project Timeline

  • March 2014 to June 2018

    City awarded contract to Sandis Engineering for design of the Project. City began outreach to the community and related partners: PAUSD, Stanford and Caltrans. City began 65% design plans.

  • July 2018

    Project was placed on hold due to staffing shortages in the Office of Transportation.

  • November 2019

    City restarted 65% project design.

  • January 2021 to May 2021

    City scheduled meetings to provide updates to the School Board, Stanford, PABAC, the City School Traffic Safety Committee and the Community.

  • June 2021 to June 2022

    Project on hold.

  • June 2022 to September 2023

    Complete 100% design plans and complete final construction documents.

  • Spring/Summer 2025

    Begin construction of the project.

  • Summer 2026

    Complete construction of the project.

 

Upcoming Meetings

There are no scheduled meetings at this time.

Past Community Meetings

May 24, 2022 - PAUSD Board Meeting
March 2, 2021 - Pedestrian and Bicycle Advisory Committee (PABAC)
February 18, 2021 - City/School Traffic Safety Committee (CSTSC)
February 9, 2021- Palo Alto Unified School District (PAUSD) Board Meeting
October 7, 2019 - City Council

 

Location

Churchill Ave at Castilleja Ave, Palo Alto, CA   View Map