Storm Drain Pump Stations and Systems Upgrades

  • Project typeCapacity Improvements

Project Descriptions

The Corporation Way System Upgrades and Pump Station, West Bayshore Road Pump Station, and West Bayshore Road Trunk Line Improvements projects are three of the highest-priority storm drain projects identified in the City’s 2015 Storm Drain Master Plan and 3 of the 13 projects identified on the 2017 ballot measure.
During a 10-year storm event, the two outfalls that convey storm runoff from East and West Bayshore Road onto Adobe Creek do not function as intended due to water pressure in the creek. Without the pump stations, this area is unable to drain until the creek levels recede, which is typically several hours after the rainfall stops. Additionally, the existing 15-inch and 24-inch storm drain pipelines do not have the capacity to convey the projected storm runoff generated by a 10-year storm event.   

Scope of Work 

The design of the three projects were advertised as one package to avoid redundant analysis and for cost savings. Schaaf and Wheeler Consulting Civil Engineers (Consultant) was selected to provide the design, prepare plans and specifications, and to provide construction administration service during construction.

Project Number   Project Name Description Project Budget  
 SD-20000 West Bayshore Road Pump Station  New small pump with 15 CFS capacity and associated improvements

 

 $1,774,653

 

 SD-21000 Corporation Way System Upgrades and Pump Station

 

 New small pump with 25 CFS capacity and associated improvements and 700 LF of pipe upgrades

 

 $3,972,333

 

 SD-23000 West Bayshore Road Trunk Line Improvements 1,400 LF of Pipe upgrades  $2,410,175

 

Project Status

The consultant is in the process of completing the design and the construction documents. The design and construction documents are scheduled to be complete for all three projects listed above by end of February 2024. 

  • Solicit bids and award contract for construction in June 2024
  • Corporation Way System Upgrades and Pump Station construction to be completed by end of Spring 2026
  • West Bayshore Road Pump Station construction to be completed by end of Spring 2026
  • West Bayshore Road Trunk line Improvements to be completed by end of  Spring 2026

Project Locations

West Bayshore Road Pump Station and Trunkline Improvements

Correct Project Location-West Bayshore Road Pump Station and Trunkline Improvement.png

East Bayshore Road Pump Station and System Upgrade

Correct Project Location-East Bayshore Road Pump Station and Trunkline Improvements.png